Pittsburgh, PA - The Pittsburgh Water and Sewer Authority (PWSA) contractors are scheduled to complete surface restoration, which includes paving and concrete work for the week of October 9, 2017. Many work locations will require restricted parking while work is being performed. Signs will be posted in advance and removed as soon as possible.

 

*Please note that the schedule is weather dependent and subject to change.

 

Work locations are as follows:

 

1413 Beldale Street

1313 Columbus Avenue

25 Strauss Street

618 Danbury Street

1128 Harvard Circle

1723 Cowley Street

1804 Penn Avenue

1421 Penn Avenue

6347 Phillips Avenue 

 

*Any customer who needs additional information should call PWSA Emergency Dispatch 24/7 at 412.255.2423.

 

-=-

 