PWSA PAVING SCHEDULE
October 16 - October 20, 2017

Pittsburgh, PA - The Pittsburgh Water and Sewer Authority (PWSA) contractors are scheduled to complete surface restoration, which includes paving and concrete work for the week of October 16, 2017. Many work locations will require restricted parking while work is being performed. Signs will be posted in advance and removed as soon as possible.

 

*Please note that the schedule is weather dependent and subject to change.

 

Work locations are as follows:

 

Welfer Street at mirror Street

934 Lilac Street

1124 Greenfield Avenue

32 Exeter Street

4524 Saline Street

4305 Lydia Street

Sedgewick Street at Lincoln Avenue  

524 Lincoln Avenue

1029 Evergreen Road

614 Lincoln Avenue

 

*Any customer who needs additional information should call PWSA Emergency Dispatch 24/7 at 412.255.2423.

 

-=-

 