PAY YOUR BILL
REPORT A PROBLEM
Press Release
PWSA LEAD SERVICE LINE REPLACEMENT SCHEDULE
September 17 – September 21, 2018

The Pittsburgh Water and Sewer Authority (PWSA) is replacing lead water service lines throughout the City of Pittsburgh to reduce exposure to lead in drinking water. PWSA will coordinate with customers to replace both portions of the lead service line when possible.

 

*Replacements will take place at the following locations from September 17, 2018 – September 21, 2018:

                        

  • Wharton Street (South 19th Street – South 20th Street)
  • Fox Way (South 19th Street – South 20th Street)
  • Plum Way (47th Street – 50th Street)
  • Kennebec Street (Frank Street – Windsor Street)
  • Alder Street (College Street – Spahr Street)
  • North Avenue (Elizabeth Street – Klopfer Street)
  • Perrysville Avenue (Waldorf Street – Franklin Road)
  • Bascom Avenue (Perrysville Avenue – Oakdale Street)
  • Ridgeville Street (Barnsdale Street – South Dallas Avenue)

 

*Please note that the schedule is weather dependent and subject to change.

Impacted residents have been notified by PWSA via letter 45 days in advance of the work. Door hangers will be posted 48 hours before replacement work will be completed. No-parking signs will be posted 24-48 hours before work begins. Interruptions in water service should last no longer than 2-3 hours.

Any customer who needs additional information should call the PWSA Lead Help Desk at 412-255-8987 or email at LeadHelp@pgh2o.com

 

 

 

  • Published
  • Monday, September 17, 2018

  • Tools
  •  
  •  
  •