Completed
Water
This project, in Pittsburgh's historic Strip District, replaced over 7,000 feet of water line, storm sewer, and sanitary sewer over the course of a year. This was a $13 million investment in the health of our system.
Progress & Status
Construction Complete
- All new water and sewer mains have been installed.
- All water service lines have been installed.
- The project site was turned over to the City of Pittsburgh's Department of Mobility and Infrastructure for eventual street redesign.
Locations & Schedule
Location Details:
Smallman Street (16th Street - 21st Street)
Start Date: May 2018
Completion Date: April 2019
Traffic Patterns: The street is now open to traffic