Completed
Water
After numerous water main breaks on this short stretch of pipe, PWSA prioritized this site for replacement in winter of 2019.
Progress & Status
Construction Complete
- New water main has been installed.
- All new water service lines have been installed.
- Concrete restoration will occur in as construction work in Spring/Summer of 2020. The PWSA restoration team will be in touch with residents to prepare for impacts of restoration.
Locations & Schedule
Start Date: December 16, 2019
Completion Date: January 13, 2020
Work Schedule: 7:00 am - 5:30 pm, Monday - Friday
Traffic Patterns: Street closed to traffic only during working hours.
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
412-255-8945
mmclaughlin@pgh2o.com