Ellsworth Place Waterline Replacement

Completed Water

After numerous water main breaks on this short stretch of pipe, PWSA prioritized this site for replacement in winter of 2019.

Progress & Status

100%
Construction Complete
  • New water main has been installed.
  • All new water service lines have been installed.
  • Concrete restoration will occur in as construction work in Spring/Summer of 2020. The PWSA restoration team will be in touch with residents to prepare for impacts of restoration.

Locations & Schedule

Start Date: December 16, 2019

Completion Date: January 13, 2020

Work Schedule: 7:00 am - 5:30 pm, Monday - Friday

Traffic Patterns: Street closed to traffic only during working hours.

Ellsworth Place project map

Ellsworth Place
Pittsburgh, PA 15232
United States