2019-2020 Street and Sidewalk Restoration Schedule

In Construction Water

After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.
We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.

Progress & Status

77%
Construction Complete

The work schedule for November 30 - December 4 is as follows: 

Paving
  • Meyran Avenue
  • Dawson Street
  • Atwood Street
  • Boundary Street
  • Howley Avenue
  • Mintwood Street
  • Carnegie Street
  • Keystone Street
  • Butler Street
  • McCandless Avenue
  • 57th Street
  • Pearl Street
  • Coral Street
  • Gross Street
  • S. Millvale Avenue
  • S. Mathilda Street
  • S. Winebiddle Street
  • Buena Vista Street
  • Labelle Street
     

All workers will maintain social distancing in the execution of their work, including when communicating with our customers. Workers will undergo health screenings. PWSA and our contractors are following strict guidelines established by the United States Centers for Disease Control and Prevention (CDC) and the Pennsylvania Department of Health related to the pandemic. The following measures are to protect the health of our workers, contractors, and you, our customer. As long as it is recommended by the CDC and PA Department of Health, all our work will occur under the following guidelines: 

  • All workers will wear face masks during their work. 
  • All work surfaces our workers are in contact with will be sanitized prior to leaving the work site. 
  • All work sites will be provided with portable hand-wash facilities or hand sanitizer. 

Locations & Schedule

Location Details:
Throughout our service area

Work Schedule: 7:00 am - 5:00 pm, M-F

Traffic Patterns: Street closures and no parking may be necessary to complete paving work.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com