This project, in the Highland Park neighborhood of the City of Pittsburgh, will will replace portions of water mains on several streets, providing more reliable water service to our customers.
Progress & Status
Crews will complete final street paving on remaining streets the week of April 24th. Portions of N. Euclid Avenue will remain under construction as gas lines are replaced.
All street and sidewalk restoration work is expected to be complete by October 2022, with some delays expected on N. St. Clair Street.
PWSA's project team spoke about this project at the Highland Park Community Council Meeting on March 17. You can view the presentation here.
Locations & Schedule
Location Details:
Highland Park
Start Date: March 14, 2022
Completion Date: Spring 2023
Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.
Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.