Baum Boulevard Water Main Replacement Project

Completed Water

This project, in the Friendship/East Liberty neighborhood of the City of Pittsburgh, will replace approximately 3,600 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after several water main breaks occurred over the past year. As part of the main replacement, we will replace all residential public water service lines, including lead water service lines, with a non-lead material.

Progress & Status

100%
Construction Complete

Locations & Schedule

Location Details:
Baum Boulevard (S. Graham Street - S. Highland Avenue)

Start Date: June 8, 2020

Completion Date: June 2021

Work Schedule: Monday – Friday from 7:00 a.m. – 7:00 p.m.

Traffic Patterns: One lane of traffic in each direction on Baum Boulevard (S. Graham Street - S. Highland Avenue) will be maintained throughout the project.

baum feature image 7-29

Baum Boulevard (S. Graham Street - S. Highland Avenue)
Pittsburgh, PA 15232
United States