This project, in the Friendship/East Liberty neighborhood of the City of Pittsburgh, will replace approximately 3,600 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after several water main breaks occurred over the past year. As part of the main replacement, we will replace all residential public water service lines, including lead water service lines, with a non-lead material.
Progress & Status
Locations & Schedule
Location Details:
Baum Boulevard (S. Graham Street - S. Highland Avenue)
Start Date: June 8, 2020
Completion Date: June 2021
Work Schedule: Monday – Friday from 7:00 a.m. – 7:00 p.m.
Traffic Patterns: One lane of traffic in each direction on Baum Boulevard (S. Graham Street - S. Highland Avenue) will be maintained throughout the project.