Bunkerhill Water Main Replacement Project

Completed Water

This project, in the Highland Park neighborhood of the City of Pittsburgh, will replace approximately 500 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement due to a history of water main breaks. As part of the main replacement, we will replace all public water service lines, including lead water service lines, with a non-lead material.

Progress & Status

100%
Construction Complete

The PWSA project team hosted a meeting to discuss the project Tuesday, October 13th, at 5:30 p.m. The project information sheet from this meeting can be found here.

  • Crews are completing final restoration of the street

Locations & Schedule

Location Details:
Bunkerhill Street (N. Highland Avenue - dead end)

Start Date: October 14, 2020

Completion Date: late November 2020

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: The street will be closed to traffic during working hours and will be plated and re-opened at the end of the work day.