Herron Avenue Water Main Replacement Project

Completed Water

This project, in the Polish Hill neighborhood of the City of Pittsburgh, will replace approximately 1,000 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after several water main breaks occurred on this portion on Herron Avenue in winter of 2017 and 2018. As part of the main replacement, we will replace all public water service lines, including lead water service lines, with a non-lead material. If a public lead service line is connected to a private lead line, we will replace it at the same time at no cost to the customer.

Progress & Status

100%
Construction Complete
  • New water main has been installed.
  • All new water service lines have been installed.
  • Paving, concrete, and line painting has been completed. 

Locations & Schedule

Start Date: June 2019

Completion Date: October 2019

Traffic Patterns: The street is now open to traffic.

Herron Avenue Project Map

Herron Avenue (Bigelow Boulevard - Cargill Street)
Pittsburgh, PA 15219