Completed
Sewer
In June of 2018, a landslide washed away an 8-inch sanitary sewer behind Odette Street in the Overbrook neighborhood of the City of Pittsburgh. This project restored normal sanitary sewer service to some customers, installed a new storm sewer as well as new storm drains in the area.
Progress & Status
Construction Complete
- All sewer lines installed
- All storm drains installed
- Street and sidewalk restoration completed
Locations & Schedule
Start Date: January 2019
Completion Date: June 2019