Lead Line Replacement Project - Elliott/Crafton Heights

In Construction Water

PWSA will work in portions of Elliott and Crafton Heights to replace all lead service lines found with a non-lead material.

Progress & Status

66%
Construction Complete

To-date, crews have accomplished the following: 

  • Crews have verified approximately 66% of all service lines in work area. 
  • Lead services line replacements continue where needed.

Locations & Schedule

Location Details:
Elliott/Crafton Heights

Start Date: March 14, 2022

Completion Date: TBD

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.

Elliott/Crafton Heights work area

Elliott/Crafton Heights
Pittsburgh , PA 15220
United States

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com