Queenston Sewer Improvements

Completed Sewer

This sewer separation project along portions of Queenston Street, Lucina Avenue, Wayside Street, and Walton Avenue in the Carrick Neighborhood will help to reduce nearby flooding and basement backups.

Progress & Status

100%
Construction Complete

Pittsburgh Water began construction on Phase II in late summer 2023. Crews will work in four mini-phases, stretching approximately one block at a time, installing new sewer pipe and connecting residents' sewer laterals to the new wastewater-only sewer. 

  • PHASE 1 (Queenston, from Fairland Street - Walton Avenue): mid August - early October
  • PHASE 2 (Queenston, from Walton Avenue - Lucina Avenue): early - mid October
  • PHASE 3 (Lucina, from Queenston Street - Englert Way, a paper street): mid October - mid November
  • PHASE 4 (Walton Avenue, Englert Way, Wayside Street): mid November - spring 2024, with some slow-down during winter months.

 

 

Phase One: Phillips Park Stormwater Project

Phase Two: Queenston Sewer Improvements

  • Separate wastewater (sanitary sewage) from stormwater in 825 feet of existing combined sewer pipes. 
  • Install new sanitary sewer pipes to convey only wastewater.
  • Convert existing combined sewer pipes into dedicated storm sewer pipes to create more room for stormwater.
  • Decommission certain existing sanitary and storm sewer pipes.
  • Possible installation of sanitary and storm sewer pipes to connect buildings to respective sewers (field and engineering investigation pending). 

Locations & Schedule

Location Details:
Queenston Street from Lucina Avenue to Fairland Street, Walton Avenue from Queenston Street to Wayside Street, and a portion of Lucina Avenue between Queenston Street and Wayside Street

Start Date: August 2023

Completion Date: Summer 2024

Map of the Queenston Sewer Improvements project area on portions of Queenston Ave, Walton Avenue, and Lucina Avenue

Queenston Street and Lucina Ave