Lead Line Replacement Programs

Burham lslr

We will complete targeted lead service lines replacements with a prioritization model that removes lead in drinking water for our most vulnerable populations. 

Lead Service Line Replacement Approaches

Neighborhood Lead Line Replacement Projects: We target all lead lines in a geographic space, passing over non-lead service lines. When a private service line is made of lead, we will work with the property owner to replace the line at no direct cost. Learn more by visiting our Community Lead Response Program page.

Water Main + Lead Service Line Replacement: This annual program targets aging water mains that also show high concentrations of lead lines attached. You can read more about this program on our Water Construction Projects page.

We have also replaced lead lines at all daycare facilities within our water service area as part of our Priority Lead Line Replacement program in 2022.

To view all lead line replacement work and see what your service line is made of, visit our Lead Map.

What to Expect During a Lead Service Line Replacement

How is a service line replaced?

Typical service line layout

Crews will start the process by going to each property and inspecting the service line material at every property. This will help determine which sites have lead service lines that need replaced. 

If both a private and public lead service line is found at a property, the Lead Help Desk will reach out and set a coordination meeting with the property owner to discuss the replacement methods and schedule a replacement date. If a customer has a public lead service line, it will be replaced at no cost and no coordinate meeting is needed.

The next step of the process is to replace the lead service line with a non-lead material. We request that the property owner or a designated representative be present on this day. We will provide a lead pitcher filter and cartridges, as well as flushing instructions, after replacement. 

The final step of the project is restoration of streets and sidewalks. You can expect a delay between the completion of your service line replacement and restoration activities.

Daily Schedule for Lead Line and Small Diameter Water Main Replacement Projects

September 15, 2026

  •  

Small Diameter Water Main Replacements

Elliot and Crafton Heights 

  • 1100 block Crucible St 
  • Lorenz Ave and Crucible St  
  • Steuben St and Lorenz Ave 
  • Berdella St (restoration)
  • Charteris Ave (restoration)
  • Crucible St (restoration)

Bloomfield

  • Ella St and Rosina Way 
  • Liberty Ave 
  • Liberty Ave and Pearl St 
  • Friendship Ave (restoration)
  • Main St (restoration)
  • Sapling Way (restoration)

Hazelwood

  • E Elizabeth St and Orinoco St
  • Renova St (inspections)   

Troy Hill

  • Gardner St
  • Lowrie St and Gardner St 

Neighborhood Lead Line Replacements

Homewood North 

  • 7200 block Race St 
  • 7300 block Hermitage St (inspections)   
  • 7300 block Idlewild St (inspections)   

Oakland 

  • Frazier St (restoration)
  • Oakland St (restoration)
  • Ward St (restoration)

Lincoln Lemington Belmar  

  • Brainard St (restoration)

South Side Slopes

  • 2500 block Josephine St 
  • Kosciusko Wy
  • Arlington Ave (restoration)
  • Berg St (restoration)

Marshall Shadeland

  • Superior Ave (restoration)

Squirrel Hill

  • Bartlett St (restoration)
  • Beacon St (restoration)
  • Hobart St (restoration)

Allegheny Center

  • 900 block Beech Ave

East Allegheny Troy Hill 

  • Spring Garden Ave (inspections)    
  • Vista St (inspections)   

Greenfield 

  • 4300 block Stanley St 
  • Alger St (restoration)
  • Greenfield Ave (restoration)
  • Hoosac St (restoration)
  • Nantasket St (restoration)
  • Neeb St (restoration)

East Liberty

  • 5500 block Baywood St 
  • 6000 block Stanton Ave 

Larimer 

  • Mayflower St (restoration)

Point Breeze

  • 300 block S Dallas Ave 
  • Carnegie Pl (restoration)
  • Lexington Ave (restoration)
  • Penn Ave (inspections)   

Point Breeze North 

  • 100 block N Linden Ave (inspections)   

Bloomfield

  • Sciota St (inspections)   

Highland Park 

  • 6300 block Stanton Ave 
  • Stanton Ave (inspections)   

 

Upcoming Lead Line Replacement Neighborhoods

In the next few months or so, we will begin lead service line replacements in portions of the following neighborhoods:

  • Bloomfield
  • Central Lawrenceville
  • Highland Park
  • Shadyside
Questions?

For lead service line replacement questions, contact the Lead Help Desk at 412-255-8987 or email LeadHelp@pgh2o.com