Pittsburgh Water will replace a portion of sewer 24-inch sewer on Carroll Street in Bloomfield. This project was selected after it was determined a portion of the 27-foot-deep combined sewer is partially collapsed. The portion of partially collapsed sewer will be replaced, restoring reliable sewer service to customers on Carroll Street.
Progress & Status
The project consists of the replacement of approximately 126-feet of 24-inch sewer and 145-feet of 15-inch sewer and associated manholes. Crews will also line approximately 600-feet of the 24-inch sewer to reinforce the pipe while avoiding additional excavation.
Locations & Schedule
Location Details:
Carroll Street (near Friendship Avenue intersection)
Start Date: April 2025
Completion Date: January 2026
Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.
Traffic Patterns: 24/7 street closure and detours around Carroll Street will be required during portions of this project. Beginning Mon. 11/10, Comrie Way will be closed to through traffic for approx. 4 weeks.