Edgerton Avenue Sewer Relocation Project

Completed Sewer

This sewer relocation project is in response to a 15-inch sewer collapse in the Point Breeze neighborhood of the City of Pittsburgh. The work includes relocating the collapsed sewer into the edge of the Homewood Cemetery.

Progress & Status

100%
Construction Complete
  • Work has been completed. 
  • Restoration will take place the week of February 10. 

Locations & Schedule

Start Date: Early 2020

Edgerton Project Map

Edgerton Avenue at South Homewood Avenue
Pittsburgh, PA 15208
United States

Project Contacts

If you have questions, please contact:

Constructions Communications Project Manager :
Mora McLaughlin
412-255-8945