Bates Street Water Main Replacement Project

Completed Water

This project, in the South Oakland neighborhood of the City of Pittsburgh, will replace approximately 1,500 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after a history of water main breaks on the water main. This work will provide more reliable water service for customers in a critical junction of the distribution system.

Progress & Status

100%
Construction Complete

The water main and all service line installation has been completed.

Locations & Schedule

Location Details:
Bates Street (Boulevard of the Allies - Second Avenue)

Start Date: June 30, 2020

Completion Date: July 30, 2020

Work Schedule: Monday – Friday from 9:00 p.m. – 5:00 a.m.

Traffic Patterns: Street will be closed to all traffic during working hours and will be reopened after working hours.