Priority Lead Line Replacement

Completed Water

PWSA will replace lead service lines at daycare facilities that are found to have lead service lines. This program will also address lead line replacements at any locations with elevated lead samples taken via our sampling program. 

Progress & Status

100%
Construction Complete

PWSA will replace lead service lines at daycare facilities that are found to have lead service lines. This program will also address lead line replacements at any locations with elevated lead samples taken via our Free Lead Test Kit Program

To date, PWSA has completed the following work:

  • Verified the service line material for 381 locations, including all daycare facilities in the PWSA service area.
  • Replaced 268 public and 301 private lead service lines.

Locations & Schedule

Location Details:
PWSA Water Service Area

Start Date: late March 2022

Completion Date: end of 2022

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Traffic will be rerouted around work areas as needed