Street and Sidewalk Restoration Schedule

In Construction Water

After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.

We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.

Percentage completion on this project refers to the total number of sites addressed as part of this construction contract and does not reference to the total number of PWSA restoration sites completed over time.

Progress & Status

22%
Construction Complete

Crews will work at the following locations today, April 25th

  • 3900 Beechwood Avenue
  • Blanton Street
  • Minnesota Street
  • 5607 Beacon Street
  • 5401 Forbes Avenue
  • 5337 Darlington Road
  • 312 Schenley Road
  • 759 Montclair Street
  • 732 Hazelwood Avenue 
  • 759 Montclair Street
  • 732 Hazelwood Avenue 
  • 508 Montclair Street
  • 515 Susanna Court
  • Susanna Street at Parade Street
  • Bigelow Street at Gladstone Street
  • 59 Bigelow Street
  • 38 Yoder Street
  • 24 Yoder Street
  • 167 Greenfield Avenue
  • Naylor Street at Levene Street
  • 408 Saline Street
  • Naylor Street at Levene Street
  • 820 Crawford Street
  • 26th at Smallman Street
  • 105 26th Street
  • 116 23rd Street
  • 4111 Beehner Road
  • 917 Wilhelm Street
  • 1115 Srawley Place
  • 426 E. Ohio Street
  • 184 N. Commons Street
  • Our Way/Stevenson Street
  • 5533 Aylesboro Avenue
  • 5629 Woodmont Street
  • 5619 Fair Oakes Street
  • 1156 S. Negley Avenue
  • 1511 Asbury Place
  • 6644 Darlington Road
  • 5607 Beacon Street
  • 5401 Forbes Avenue
  • 5337 Darlington Road
  • Tech Street Roadway
  • 1600 Beechwood Boulevard
  • 603 Johnston Avenue
  • 740 Greenfield Avenue
  • 3900 Beachwood Boulevard

 

 

work is weather-dependent and subject to change

Locations & Schedule

Location Details:
Throughout service area

Start Date: Ongoing

Completion Date: Ongoing

Work Schedule: 7:00 am - 5:00 pm, M-F

Traffic Patterns: Street closures and no parking may be necessary to complete paving work.