Water Main Replacement Project - Lower Lawrenceville

In Construction Water

This project, in the Lower Lawrenceville neighborhood of the City of Pittsburgh, will replace three water mains on several streets, providing more reliable water service to our customers.

Progress & Status

40%
Construction Complete

Crews have begun exploratory digging to prepare for new water main installations and service line material verifications on Ligonier Avenue.

Work will occur on the following streets: 

  • Liberty Avenue
  • Ligonier Avenue
  • Spring Way
  • Sardis Way
  • Cabinet Way

Locations & Schedule

Location Details:
Lower Lawrenceville

Start Date: August 2025

Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.

Traffic Patterns: Crews will replace water mains and any lead service lines found within the project area.

Lower Lawrenceville
Pittsburgh, PA 15201
United States