2020 Water Main Replacement - Hazelwood

In Construction Water

This project, in the Hazelwood neighborhood of the City of Pittsburgh, will replace portions of water mains on several streets, providing more reliable water service to our customers.

Progress & Status

30%
Construction Complete

On Thursday, November 12, the PWSA project team hosted a community meeting to inform residents of the project and answer any questions they may have. You can watch a recording of the meeting here

Read the Project Information Sheet shared at the community meeting here.

Crews will replace water mains on the following streets: 

  • Tecumseh Street - ACTIVE
    • (Blair Street - Langhorn Street) - Water main is being tested
    • (Blair Street - Gloster Street) - Service lines are being installed
  • Langhorn Street - ACTIVE
    • Water main is being tested
  • Courtland Street - ACTIVE
    • (Langhorn Street - Blair Street) - water main is being tested 
  • Blair Street - ACTIVE
    • Water main is being installed
  • Gloster Street - ACTIVE
    • Water main is being installed
  • West Elizabeth Street - ACTIVE
    • Water main is being installed

Locations & Schedule

Location Details:
Hazelwood neighborhood

Start Date: December 1, 2020

Completion Date: Spring 2020

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com