This project, in the Borough of Millvale, will replace the water main on Evergreen Road, between Ohio Street and Klopfer Street, providing more reliable water service to our customers.
Progress & Status
On March 3, 2021, PWSA's project team hosted a virtual community meeting. To view the presentation, click here.
Crews will replace the water main on Evergreen Road (Ohio Street - Klopfer Street). Work will be completed in stages to minimize street closures.
- Evergreen Avenue (Ohio Street - Sheridan Street) - Water main is being constructed)
Locations & Schedule
Location Details:
Borough of Millvale
Start Date: April 2021
Completion Date: September 2021
Work Schedule: 7:00 a.m. - 4:00 p.m., Monday-Friday
Traffic Patterns: Portions of Evergreen Road will be closed to traffic during working hours and reopened at the end of the work day.
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com