2020 Water Main Replacement - Millvale

In Construction Water

This project, in the Borough of Millvale, will replace the water main on Evergreen Road, between Ohio Street and Klopfer Street, providing more reliable water service to our customers.

Progress & Status

10%
Construction Complete

On March 3, 2021, PWSA's project team hosted a virtual community meeting. To view the presentation, click here.

Crews will replace the water main on Evergreen Road (Ohio Street - Klopfer Street). Work will be completed in stages to minimize street closures. 

  • Evergreen Avenue (Ohio Street - Sheridan Street) - Water main is being constructed)

Locations & Schedule

Location Details:
Borough of Millvale

Start Date: April 2021

Completion Date: September 2021

Work Schedule: 7:00 a.m. - 4:00 p.m., Monday-Friday

Traffic Patterns: Portions of Evergreen Road will be closed to traffic during working hours and reopened at the end of the work day.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137