This project, in the Mount Washington and Duquesne Heights neighborhoods of the City of Pittsburgh, will replace portions of water mains on several streets, providing more reliable water service to our customers.
Progress & Status
The PWSA project team hosted a virtual community meeting about upcoming work on February 4th. To see the presentation from this meeting, click here.
Crews will replace water mains on the following streets:
- Meridan Street - ACTIVE
- Water main is in construction
- Meta Street - ACTIVE
- Water main is in construction
- Westwood Street
- Smith Way
- Wyola Street
- Clarence Street
- Mann Street
- Rubicon Street
- Cuthbert Street
- Guerdon Way
- Gaskell Street
- Grace Street
- Beam Way
Locations & Schedule
Location Details:
Mount Washington and Duquesne Heights
Start Date: January 2020
Completion Date: May 2021
Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.
Traffic Patterns: Streets will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.
PA
United States
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
412-689-4137