2020 Water Main Replacement - Mount Washington, Duquesne Heights

In Construction Water

This project, in the Mount Washington and Duquesne Heights neighborhoods of the City of Pittsburgh, will replace portions of water mains on several streets, providing more reliable water service to our customers.

Progress & Status

15%
Construction Complete

The PWSA project team hosted a virtual community meeting about upcoming work on February 4th. To see the presentation from this meeting, click here.

Crews will replace water mains on the following streets: 

  • Meridan Street - ACTIVE
    • Water main is in construction
  • Meta Street - ACTIVE
    • Water main is in construction
  • Westwood Street
  • Smith Way
  • Wyola Street
  • Clarence Street
  • Mann Street
  • Rubicon Street
  • Cuthbert Street
  • Guerdon Way
  • Gaskell Street
  • Grace Street
  • Beam Way

Locations & Schedule

Location Details:
Mount Washington and Duquesne Heights

Start Date: January 2020

Completion Date: May 2021

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.

PA