2020 Water Main Replacement - South Side Slopes

In Construction Water

This project, in the South Side Slopes neighborhood of the City of Pittsburgh, will replace portions of water mains on several streets, providing more reliable water service to our customers. Phase II of this work was completed in

Progress & Status

55%
Construction Complete
Upcoming - Late March 2021
  • Oporto Street 
  • Roscoe Street
  • Burham Street
  • Sumner Street
  • Stromberg Street
  • Cobden Street
  • Salisbury Street
  • Eleanor Street
  • Berg Street
  • Northview Street
Completed Streets:
  • Industry Street
  • Mount Oliver Street 
  • Loyal Way 
  • Magdalene Street 
  • Saint Leo Street
  • Crossman Street
  • Saint Patrick Street 
  • Gable Street 
  • Angelo Street 
  • St. Thomas Street 
  • Monastery Avenue 
  • Monastery Place 
  • Nusser Street 
  • South 18th Street 

Locations & Schedule

Location Details:
South Side Slopes

Start Date: June 2020

Completion Date: Summer 2021

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: The street will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.

PA
United States

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com