2022 Water Main Replacement - Shadyside/Squirrel Hill

In Planning Water

This project, in the Shadyside and Squirrel Hill North neighborhoods of the City of Pittsburgh, will will replace portions of water mains on several streets, providing more reliable water service to our customers.

Progress & Status

60%
Design Complete

Crews will replace water mains on the following streets:

  • Morewood Avenue (Ellsworth Avenue - 5th Avenue) - crews testing the new water main
  • Bellerock Street (Wilkins Avenue - Woodmont Street) - crews are installing new hydrants and storm drains, testing new water main
  • Castleman Street (Morewood Avenue - midway to Amberson Avenue) - crews are testing the new water main
  • Gladstone Road - crews will restore the street and sidewalks in Spring 2023

Locations & Schedule

Location Details:
Shadyside/Squirrel Hill North

Start Date: mid-December 2022

Completion Date: Spring 2023

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.

Shadyside project map

PA
United States

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com