This project, in the Shadyside and Squirrel Hill North neighborhoods of the City of Pittsburgh, will will replace portions of water mains on several streets, providing more reliable water service to our customers.
Progress & Status
Crews will replace water mains on the following streets:
- Morewood Avenue (Ellsworth Avenue - 5th Avenue) - crews testing the new water main
- Bellerock Street (Wilkins Avenue - Woodmont Street) - crews are installing new hydrants and storm drains, testing new water main
- Castleman Street (Morewood Avenue - midway to Amberson Avenue) - crews are testing the new water main
- Gladstone Road - crews will restore the street and sidewalks in Spring 2023
Locations & Schedule
Location Details:
Shadyside/Squirrel Hill North
Start Date: mid-December 2022
Completion Date: Spring 2023
Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.
Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com