31st Ward Sewer Reconstruction Project

In Construction Sewer

This $2.9 million project, taking place in the Lincoln Place neighborhood of the City of Pittsburgh, will line approximately 5 miles of aging sewers, repair broken sewers, relocate storm drains, and separate combined storm and sanitary sewers where needed. Work will be completed at numerous locations throughout the neighborhood and residents will be notified via letter, robocall, door hanger, or a combination of the three, when work may impact them. Lining and repairing these sewers will extend the life of the sewer system and ensure better service to our customers.

Progress & Status

45%
Construction Complete
  • Sewer lining work continues throughout area. Customers will be notified of work via door hangers.
  • Crews are completing sewer replacement on Nollhill Street. Customers in the vicinity of the work have been notified via letters.

Locations & Schedule

Location Details:
Locations throughout Lincoln Place neighborhood

Start Date: Summer 2020

Completion Date: Summer 2021

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Detour signs will be placed around sewer work when necessary.

31st Ward GIS Map

United States

Project Contacts

If you have any questions, please contact:

PWSA Project Manager :
Manda Metzger
412-255-8800 x 8515
mmetzger@pgh2o.com

Construction Communications Project Manager :
Mora McLaughlin
412-255-8945
mmclaughlin@pgh2o.com