In partnership with the City of Pittsburgh, we are planning a stormwater and roadway improvements project to address flooding issues at Braywood Way in the Greenfield and Hazelwood neighborhoods.
Progress & Status
Construction is anticipated to begin October. 14
PWSA's project team provided two virtual presentations with residents so far in the design process:
The project area is located in the M-29 sewershed, one of the largest contributors to combined sewer overflows (CSOs) into rivers in the Pittsburgh region. Therefore, stormwater detention and/or green infrastructure measures will be prioritized during design.
Project Components
- Design and install infrastructure to help manage stormwater flows that are impacting private properties, the roadway, and the Monongahela River via CSOs
- Prioritize stormwater detention and/or other green infrastructure systems where peak flows from the watershed can potentially be captured and managed
- Design and install roadway improvements to enhance both road surface quality and drainage
Locations & Schedule
Location Details:
Greenfield and Hazelwood neighborhoods
Start Date: late-October
Completion Date: Spring 2025
Work Schedule: Monday-Thursday, 7:00 a.m. - 5:00 p.m.
Traffic Patterns: The intersection of Bray Street at Braywood Way will remain closed 24/7 while the stormwater retention tanks are being installed.
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
412-689-4137