Fleury Way Sewer Replacement Project

In Construction Stormwater

This project replaced approximately 750-feet of sewer on Fleury Way, between N. Murtland Street and N. Dallas Avenue. This project will improve stormwater drainage within the alleyway. As part of this work, PWSA contractor crews will also rebuild the alleyway after structural deficiencies were found during sewer work.

Progress & Status

80%
Construction Complete

Beginning the week of September 5th, contractor crews began rebuilding the street, curbs, and sidewalks along Fleury Way. Crews will complete work by Thanksgiving 2022.

Locations & Schedule

Location Details:
Fleury Way (N. Murtland Street - N. Dallas Avenue)

Start Date: spring 2021

Completion Date: late-November 2022

Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.

Traffic Patterns: The street will remain closed to all traffic until work is complete

Project Contacts

If you have questions, please contact

Construction Communication Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com