High Park Place Water Main Replacement Project

In Construction Water

This project, in the Highland Park neighborhood of the City of Pittsburgh, will replace approximately 350 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after several water main breaks occurred over the past year. As part of the main replacement, we will replace water service lines, including lead water service lines, with a non-lead material.

Progress & Status

95%
Construction Complete
  • All water main and new service lines are installed.
  • Crews are restoring street and sidewalks that were disturbed as part of the work. Restoration work is anticipated to take two weeks, making the final completion of the project April 23rd.

 

Locations & Schedule

Location Details:
Virtual meeting

Start Date: late-March, 2021

Completion Date: April 23, 2021

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.

High Park Place
Pittsburgh, PA 15206
United States

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-689-4137
mmclaughlin@pgh2o.com