Highland I Reservoir Security Improvements

In Construction Water

To maintain the open Highland I Reservoir as a public amenity, we are constructing several projects to meet stricter state water quality regulations and security improvements. These projects will improve the security of our drinking water.

Progress & Status

70%
Construction Complete

Restoration of the parapet wall around the Highland I Reservoir

  • The majority of the construction on the first half of the wall is complete. The contractor is setting the hand railing.
  • Demolition is complete on the second half of the wall. 
  • Construction of this portion of the new wall is underway. The contractor is using a mobile concrete slip forming machine to pour the concrete. 
  • This machine moves along the edge of the wall as concrete pours into each section allowing the contractor to continuously move from one section to the next. 
  • Extensive deterioration of portions of the wall base was discovered during the demolition of the second half of the wall. The contractor will replace this 460-foot section of the base. 
  • Once the wall is complete, the contractor will restore the walkway around the reservoir. This is dependent on the availability of asphalt suppliers as COVID-19 restrictions are lifted and they reopen. This could possibly cause a project delay. 

Completed installation of ultraviolet disinfection at the Membrane Filtration Plant (MFP) on Reservoir Drive

Completed installation of security cameras to provide a 360-degree view of the reservoir and surrounding walkway

Restoring the parapet wall

All of the projects, with the exception of the parapet wall, were completed this summer. The restoration work began in September and will continue through Spring 2020. During construction, the public will not have access to the walkway around the reservoir. We are closing it to expedite the work and maintain public safety while construction is taking place. 

Press Release: Restoration of Parapet Wall Begins

Locations & Schedule

Start Date: Spring 2019

Completion Date: Spring 2020

Work Schedule: 8:00 am to 5:00 pm Monday through Friday

Traffic Patterns: The walkway around the Highland I Reservoir is closed

Map of the Highland I Reservoir in Highland Park

Highland Park Reservoir
Pittsburgh, PA 15206
United States

Project Contacts

If you have questions, please contact the Project Manager

Project Manager :
Brad McShane
412-255-8800 ext 2504
bmcshane@pgh2o.com

If you have questions, please contact Public Affairs

Communications Project Manager :
Rebecca Zito
412-676-6684
rzito@pgh2o.com