Completed
Water
PWSA will work in portions of Hazelwood to replace all lead service lines found with a non-lead material.
Progress & Status
Construction Complete
PWSA hosted a project meeting for residents within the work area on Tuesday, June 27th. Click here to view the presentation.
Locations & Schedule
Location Details:
Hazelwood
Start Date: mid-June 2023
Completion Date: August 2023
Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.
Traffic Patterns: Street closures will be posted throughout the project area as needed.