Lead Line Replacement Project - North Oakland

In Construction Water

PWSA will work in portions of North and South Oakland to replace all lead service lines found with a non-lead material.

Progress & Status

95%
Construction Complete
  • Crews are completing street and sidewalk restoration at some locations.

Locations & Schedule

Location Details:
North Oakland

Start Date: mid-June 2022

Completion Date: fall 2022

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.

North Oakland project area

North Oakland
Pittsburgh, PA 15213
United States

Project Contacts

If you have questions, please contact

:
Lead Help Desk
412-255-8987