In Construction
Water
PWSA will work in portions of Squirrel Hill to replace all lead service lines found with a non-lead material.
Progress & Status
Construction Complete
PWSA will host a virtual community meeting on Wednesday, April 12, at 6:00 p.m., to discuss the project and answer any questions you may have. To join the meeting, visit our event page.
Crews are finishing inspections of all service lines within project area, with some lead line replacements ongoing.
Locations & Schedule
Location Details:
Squirrel Hill North
Start Date: April 2023
Completion Date: Mid-May 2023
Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.