Lead Line Replacement Project - Squirrel Hill

In Construction Water

PWSA will work in portions of Squirrel Hill to replace all lead service lines found with a non-lead material.

Progress & Status

95%
Construction Complete

PWSA will host a virtual community meeting on Wednesday, April 12, at 6:00 p.m., to discuss the project and answer any questions you may have. To join the meeting, visit our event page

Crews have replaced any lead lines found within the project area and are now restoring streets and sidewalks.

Locations & Schedule

Location Details:
Squirrel Hill North

Start Date: April 2023

Completion Date: Mid-May 2023

Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.

Traffic Patterns: Street closures will be posted throughout the project area as needed.

Project Contacts

If you have questions, please contact

:
Lead Help Desk
412-255-8987