Water Main Replacement Project - Millvale

In Construction Water

This project, in Millvale Borough, will replace portions of water mains on several streets, providing more reliable water service to our customers.

Progress & Status

55%
Construction Complete
  • Clara Street - work is complete, street and sidewalks will be restored
  • Beckert Street - work is complete, street and sidewalks will be restored
  • Van Buren Street - work is complete, street and sidewalks will be restored
  • Siegel Street - work is complete, street and sidewalks will be restored
  • Davis Street - service line installation in progress
  • Lippert Street - work is complete, street and sidewalks will be restored
  • Lincoln Avenue - service line installation in progress
  • Sherman Street - service line installation in progress
  • Grant Avenue - service line installation in progress
  • Sheridan Street - service line installation in progress
  • Fornoff Street - work is complete, street and sidewalks will be restored

Locations & Schedule

Start Date: Summer 2023

Completion Date: Summer 2024

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: The street will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin

mmclaughlin@pgh2o.com